DATA CENTER ENERGY SOLUTIONS

Data center power.
From interface to backup.

Explore transformer, battery and backup-power interfaces through a U.S. data center demonstration, then define the equipment and evidence your own project needs.

Discuss a data center project
U.S. INDUSTRY CASE / CHEYENNE, WYOMING

What a 48-hour backup demonstration teaches us about data center power.

Microsoft hosted a demonstration led by Caterpillar with Ballard fuel-cell technology. The useful procurement lesson is how power conversion, transformers, batteries and controls work together.

Independent analysis of a publicly documented demonstration reported in 2024. WAYTON did not supply or deliver this project.

Concept data center campus with transformer yard, switchgear and battery enclosures
AI-generated concept visualisation. Not a photograph or reconstruction of Microsoft’s Cheyenne project.
1.5 MWReported fuel-cell rating
2 systemsCat PGS 1260 battery storage
48 hoursSimulated backup event
1,855 mReported test-site elevation

Source: Caterpillar, 19 January 2024 ↗. These figures describe the demonstration, not the campus’s total capacity or a WAYTON product specification.

The engineering problem

A data center needs continuity during a supply interruption, followed by sustained backup operation. A source’s megawatt rating alone cannot establish transfer performance, load acceptance or the duration of available energy.

The Cheyenne project combined a hydrogen source with batteries and supervisory controls. It was tested at altitude and below freezing. Those conditions make equipment qualification and integration more informative than a simple equipment list.

What the public record establishes

The DOE technical presentation describes an inverter, transformer and switchgear alongside the fuel cell and two battery sources. It also describes islanded operation with a load bank. Treat this as a documented demonstration, not evidence that the entire campus ran islanded for 48 hours.

Transformer MVA, winding voltages, impedance, vector group and the complete site single-line diagram are not specified in the cited overview. They cannot be inferred from the fuel-cell rating.

Equipment roles and interfaces
Hydrogen supplySustained fuel availability
→
Fuel cell + inverterDC generation → AC conversion
→
Transformer + switchgearVoltage interface · switching · protection coordination
→
Electrical system / test loadDefined connection boundary
Battery storage ↔ electrical systemDynamic power support and energy bufferingMicrogrid controller ⇢ coordinated equipmentSupervisory control; dashed arrow denotes control, not power

Functional interpretation based on the DOE presentation. This is not the project’s as-built single-line diagram; exact branch positions, UPS topology and protection details are not reproduced.

Oil-immersed transformer product reference
Voltage interfaceTransformer selection starts with the bus voltages, load and protection study.Explore transformer options →
Outdoor battery cabinet product reference
Power and energyAssess discharge rating, usable energy and control compatibility separately.Explore battery storage →

Product-category illustrations from the WAYTON website. These are not the equipment installed in the Cheyenne demonstration or a confirmed selection for a U.S. data center.

The transformer deserves its own specification.

Its presence is confirmed in the DOE presentation. Its project-specific rating is not. For a new project, the designer must establish the following requirements before a supplier proposes equipment.

DecisionWhat to establishWhy it changes procurement
Voltage and frequencyActual utility, inverter and bus voltages; required operating frequencyDefines ratio, taps and insulation requirements. Do not assume one voltage for every U.S. site.
kVA and operating dutyDesign load, power factor, expansion stages and applicable overload dutyIT load alone omits cooling and other facility loads; inverter kW alone does not define transformer kVA.
Faults and groundingImpedance, winding connection, neutral treatment and protection studyAffects fault current, equipment withstand and selective isolation.
Power electronicsHarmonic spectrum, energization behavior and reverse-power duty where applicableRequires coordination with inverter limits, losses and protection settings.
Site and acceptanceAltitude, ambient conditions, enclosure, installation and specified test evidenceEstablishes thermal suitability, access and the factory/site acceptance scope.
WORKED EXAMPLE / ASSUMPTIONS, NOT CHEYENNE DATA

Power and duration answer different questions.

Assume a constant 1 MW load. Delivered energy equals power × time, before conversion losses, reserve, ageing or usable-state-of-charge limits.

5 minutes83 kWh
15 minutes250 kWh
60 minutes1,000 kWh

A nominal 261 kWh cabinet is therefore not automatically a 1 MW, 15-minute backup solution. Its discharge power, usable energy, transfer behavior and system compatibility must all meet the requirement.

For a separate transformer screening example, assume 2 MW of coincident facility demand at 0.95 power factor: 2 ÷ 0.95 = 2.11 MVA before design allowances. This is a starting calculation, not a final transformer rating or redundancy design.

Specify an operating sequence, then test it.

01 / Supply interruption

Define which loads must remain uninterrupted and which equipment bridges the transition. Specify measured transfer and voltage/frequency acceptance criteria.

02 / Backup source acceptance

Test starting, ramp-up and load steps against the agreed limits. Verify battery state-of-charge reserve and control behavior.

03 / Sustained operation

Confirm fuel or stored-energy availability, auxiliary loads, thermal conditions and response to a component becoming unavailable.

04 / Return to normal

Define reconnection, synchronization where required, battery recharge and return to standby without compromising the protected load.

These are WAYTON’s proposed discussion points for a new project, not a reconstruction of Cheyenne’s test procedure. Outdoor BESS does not replace a UPS by default, and this case does not establish a Tier certification or availability guarantee.

TURN THE CASE INTO YOUR EQUIPMENT BRIEF

Bring the single-line diagram. Define the supply boundary.

Share bus voltages, facility demand, critical load, backup duration and site conditions. WAYTON can help coordinate transformer options, BESS suitability and technical submittals against your designer’s specification. Confirm U.S. project approvals, acceptance tests and service responsibilities for the exact configuration; Italian CEI documentation does not establish U.S. approval.

Discuss equipment scope ↗

Public sources

Caterpillar: demonstration announcement, January 2024 ↗
U.S. DOE: technical webinar transcript, February 2024 ↗

Published project facts are separated above from illustrative calculations and WAYTON’s equipment-selection interpretation.

EQUIPMENT & PROJECT COORDINATION
01 / POWER DISTRIBUTION

Transformer selection

Discuss MV/LV voltage levels, transformer rating, losses, cooling method, installation conditions and the required test documentation.

Explore transformers
02 / ENERGY STORAGE

Battery system options

Evaluate BESS for the specified use case, including energy management or a separately engineered backup system. Confirm power, energy, controls and protection requirements.

Explore energy storage
03 / SYSTEM INTERFACES

A coordinated equipment scope

Define interfaces with switchgear, UPS, generators, protection and monitoring systems. Agree supply responsibilities with your electrical designer and system integrator.

Discuss system requirements

Outdoor BESS is not a drop-in replacement for a UPS. Backup capability, transfer performance, redundancy and compliance must be assessed against the complete system design.

YOUR PROJECT BRIEF

What we need
to get started.

  1. Project location, facility type and target delivery schedule.
  2. IT load and total facility load, including phased expansion.
  3. Single-line diagram, voltage levels and utility connection details.
  4. Required redundancy, maintainability and backup duration.
  5. UPS and generator interfaces, protection and control requirements.
  6. Applicable project standards, acceptance tests and service scope.

A focused partner for your power project.

Competitive equipment pricing, careful selection and dedicated project attention.

Start your project brief
PROJECT QUESTIONS

Equipment selection, explained.

Clear answers to help you define the equipment scope and the next step.

What does WAYTON provide for data center projects?

WAYTON supports transformer selection, battery system evaluation and equipment supply coordination. The equipment scope is aligned with the electrical designer, system integrator and the project power architecture.

Which information is needed to begin?

Share the IT load, total facility load, single-line diagram, voltage levels and phased expansion plan. Specify the redundancy requirements, backup duration, equipment interfaces, acceptance tests and service responsibilities.

Does WAYTON promise a particular resilience or certification level?

No level should be assumed from a product category alone. Resilience, maintainability and compliance are assessed against the complete project design and confirmed equipment scope.

Read our energy equipment selection guide