Give suppliers a decision-ready starting point.

A useful project brief states the operating objective, known constraints and decisions still open. You do not need a finished design to start a discussion, but a target capacity without a load profile or connection boundary rarely supports a dependable equipment proposal.

Use a one-page brief with supporting files.

FieldUseful entryAvoid
ObjectiveReduce a measured evening import peakWe need a battery
DemandInterval data with units, dates and meter locationA monthly bill presented as a peak-load profile
ConnectionAvailable capacity, voltage, frequency and single-line diagramAssuming transformer nameplate equals spare site capacity
SiteLocation, space, access and environmental conditionsCountry name only
ProgrammeRequired operating date and procurement milestonesAn unqualified urgent deadline
Open decisionsExport limit and backup scope awaiting confirmationLeaving unknowns blank

Example: turn a request into an engineering question.

ILLUSTRATIVE EXAMPLE · NOT A PROJECT QUOTATION

Initial request: “Quote a 261 kWh cabinet.” Better brief: “Our illustrative factory imports 180 kW for 90 minutes after production ramps up. We want to assess a 120 kW import ceiling. Please evaluate a 60 kW discharge duty and at least 90 kWh delivered to the load, with usable capacity, losses and reserve stated separately.”

The example defines a duty, not a final product. Include recharge opportunities, seasonal variation and the frequency of the event. Backup, if required, needs its own critical-load list and transfer-performance requirements.

Attach the right evidence.

Provide the current single-line diagram, equipment list, interval energy data, layout and relevant utility correspondence. Label each file with a date and revision. For a retrofit, identify existing inverter, transformer, protection and control equipment. For a new build, distinguish approved requirements from preliminary assumptions.

Make the next deliverable explicit.

StageExpected output
Initial reviewMissing-information list and proposed equipment boundary
Technical alignmentSelected configuration, interface questions and deviations
Commercial proposalPriced scope, exclusions, programme and service responsibilities
Order readinessAgreed documents, tests and change-control process

Send the brief through our contact page. WAYTON can help organize equipment options and supplier responses around the stated requirement.