A lower quotation can contain a smaller scope.

Compare equipment offers against one written requirement, then normalize the exclusions. The goal is to identify which offer meets the required duty with a clear delivery and service boundary. An unanswered technical requirement should remain an open item, rather than being treated as included.

Build a common comparison sheet.

CompareEvidence to requestQuestion to resolve
Equipment configurationModel, quantity, selected options and revisionAre ratings for the same duty and ambient conditions?
System interfacesSupply boundary drawing and interface listWho supplies protection, controls, cables and accessories?
DeliveryNamed destination, delivery basis and programmeWhich logistics and site-handling costs remain with the buyer?
AcceptanceFactory/site test schedule and acceptance criteriaWhat evidence is required before payment or handover?
ServiceWarranty terms, labour/travel scope and support routeWho responds, and what work is actually covered?

Normalize cost before ranking offers.

ILLUSTRATIVE EXAMPLE · NOT A PROJECT QUOTATION

Assume Offer A is €90,000 for equipment only. Your comparison adds €8,000 for the required controls and €7,000 for agreed commissioning: €105,000. Offer B is €102,000 including those same items. On this limited scope, B is €3,000 lower. These invented numbers exclude taxes, financing and other costs; they demonstrate a method, not market prices.

Keep estimated additions distinct from supplier-confirmed prices. An unpriced exclusion is a commercial uncertainty; do not hide it inside a precise total.

Separate pass/fail requirements from preferences.

First check essential compatibility, documentation and acceptance requirements. Then compare price, delivery, service and operating costs among compliant offers. A weighted score should not allow a low price to compensate for an unmet essential requirement.

Close the review with a deviation register.

ItemSupplier positionRequired next action
Specified test reportNot included in offerConfirm availability, cost and delivery date
Control interfaceProtocol named; signals undefinedAgree signal list and responsibility for integration
CommissioningRemote support onlyAssign on-site work and acceptance sign-off

Send the same clarification questions to each shortlisted supplier. Record the final quotation revision and carry agreed answers into the order specification. WAYTON can coordinate this comparison and supplier clarification process.